Jul 27th, 2009 by Kawshala Kapila
- Plastering of front Sky wall continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Continued repairing of Louvers of windows
- Started laying of roof tiles on small pavilions.
- Work delayed due to rain
Posted in Progress | No Comments »
Jul 27th, 2009 by Kawshala Kapila
- Plastering of front Sky wall continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Continued repairing of Louvers of windows
- Roof tile transported to the site
Posted in Progress | No Comments »
Jul 27th, 2009 by Kawshala Kapila
- The Form Work of Pillars of the Makara Thorana completed
- Casting of Walakulu Bemma on the South Boundary wall completed. Plastering of front Sky wall continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Continued repairing of Louvers of windows
- Work delayed due to rain
Posted in Progress | No Comments »
Jul 27th, 2009 by Kawshala Kapila
- The Form Work of Pillars of the Makara Thorana continued
- Casting of Walakulu Bemma on the South Boundary wall continued. Plastering of front Sky wall continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Continued repairing of Louvers of windows
- Work delayed due to rain
Posted in Progress | No Comments »
Jul 27th, 2009 by Kawshala Kapila
- The Monks were invited for the Wassana Kala in the morning and the delegation left Lumbini.
- The Form Work of Pillars of the Makara Thorana continued
- Casting of Walakulu Bemma on the South Boundary wall continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Continued repairing of Louvers of windows
Posted in Progress | No Comments »
Jul 27th, 2009 by Kawshala Kapila
- The new website for the Sri Lanka Maha Vihara (www.lumbinisudeesa.org) was launched by Mr. Thosapala Hewage H.E. The Sri Lankan Ambassador for Nepal with the chanting of Seth Pirith
- The site was inspected by Mr. Thosapala Hewage H.E. The Sri Lankan Ambassador for Nepal with the Comiittee.
- A meeting was held in the evening to discuss about the progress and the future plans
- The Form Work of Pillars of the Makara Thorana continued
- Casting of Walakulu Bemma on the South Boundary wall continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Continued repairing of Louvers of windows
Posted in Progress | No Comments »
Jun 30th, 2009 by Kawshala Kapila
- The Form Work of Pillars of the Makara Thorana continued
- Casting of Walakulu Bemma on the South Boundary wall continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Continued repairing of Louvers of windows
Posted in Progress | No Comments »
Jun 30th, 2009 by Kawshala Kapila
- The Pillars of the Makara Thorana concreted
- Casting of Walakulu Bemma on the South Boundary wall continued
- Continued repairing of Louvers of windows
- Continued cutting & polishing of Marble. Final touches of Steps continued
Posted in Progress | No Comments »
Jun 30th, 2009 by Kawshala Kapila
- A rainy day. No work done
- Continued repairing of Louvers of windows
Posted in Progress | No Comments »
Jun 30th, 2009 by Kawshala Kapila
- The Form Work of Pillars of the Makara Thorana continued
- Casting of Walakulu Bemma on the South Boundary wall and Plastering of North Walakulu Bemma continued
- Replacement of roof tiles started on Resource Center
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Continued repairing of Louvers of windows
Posted in Progress | No Comments »